Services Provider

Project Name:

Servilla Hydropower Plant Modernization Project

Project Time:

2025

Project Introduction:

Location:Bohol Island, Philippines 

Owner:BOHECO I Electric Cooperative 

Existing Facility: 2.32 MW installed capacity (2 x 1.16 MW Kaplan turbines with automatic blade adjustment) 

 Project Scope:

We are executing a comprehensive modernization of the Bohol Hydropower Plant, delivering: 

1. Design & Supply: Advanced electromechanical equipment tailored for Kaplan turbine efficiency gains. 

2. Installation & Commissioning: Seamless integration with minimal operational disruption. 

3. Testing & Operational Handover: Guaranteed performance validation. 

4. Operator Training: Building local expertise for sustainable plant management. 


Key Objectives:

* Boost Efficiency: Optimize output of existing Kaplan units through modern control systems.
* Enhance Reliability: Upgrade critical components for stable power supply to Bohol Island.
* Extend Asset Life: Implement future-proof solutions ensuring long-term performance.
* Strengthen Local Capacity: Empower BOHECO I through comprehensive knowledge transfer.


Delivering Value for BOHECO I:

This upgrade ensures the plant continues to provide clean, reliable, and cost-effective electricity for Bohol communities while maximizing the return on existing infrastructure.